Step-by-Step Installation of the Prefabricated Econox Building System
Delivery
Wall and roof panels are delivered assembled and folded.
Opening
Sections are unfolded using light lifting equipment.
Installation
The four-panel section is placed on the foundations. Only one day is needed to install six sections to form a 40 ft x 60 ft (12 m x 18 m) building.
Fastening
The panels are bolted together and knee braces are attached to the panel framing.
Finishing
At the end of the first day, all sections are installed. During the second day, the end panels will be assembled and the interior caps will be sealed and installed.